Commissioning

Commissioning

After you finish the installation of the charging station, configure the parameters of the station.

The charging station may come pre-configured if the customer specified their preferences during the ordering process. In such instances, the charging station is ready for immediate use. Nonetheless, it is strongly advisable to review the configured parameters to ensure they align with the user's specific requirements.

 

The charging station can be configured via the INCH Core mobile app or a central system known as the charge point management system. 

For more information on the mobile application, refer to the INCH Core app.

 


Phone-CoreApp.png

 

  1. Open the INCH Core app.

  2. In the Main menu, select Charging stations.

  3. Add the charging station to the Charging stations screen. Once you have successfully added it, the app guides you to scan the charging station’s QR code found on the installer interface.

 

The scanning of the QR code is needed for pairing the app with the station.


18-MainUnit-QRCodeScanning.png
  1. Scan the QR code and follow the further instructions given by the app.

 

 If the charging station connection:

  • is successfully established, follow the next step.

  • was not established, refer to Troubleshooting and try again.


Phone-CoreApp.png
  1. Once the connection is successfully established, set the parameters of the charging station (via INCH Core app) if they have not already been set.

 

If the device is already configured, it is highly recommended to review the set parameters.


SwipeLoadGuard-ChargStation2.png
  1. (Optional) In case you want to install Load Guard during the installation of the charging station, pair it with the station before installing the front cover on the Main unit. Approach the Load Guard close to the front of the LED and button area to pair it with the module using RFID.

 

The pairing of the Load Guard with the charging station can also be done at any later time when the front cover is removed. The pairing cannot be done when the front cover is in place.

 

For more information, refer to the INCH Core Load Guard user documentation.


19-MainUnit-FrontCover-Assembling2.png

 

  1. Place the front cover of the Main unit module in its position. First insert the fastening hook of the front cover into the hook slot, then bring the lower right part of the cover closer to the installer interface until it is covered.


20-MainUnit-FrontCover-Assembling4xClick-Screw.png

 

  1. Press the cover until it snaps into place (four snap-fit points) and secure it with the screw. Tighten the screw with the appropriate torque. Use the provided screwdriver.

 

 

Once the front cover is installed, the installer interface mode switches to the end-user interface.
When the front cover is not in place, the charging functionality is disabled and is not possible.

 

 

 

Warning! Before installing, wiring, handling or accessing the charging station in any way, make sure to read, understand and follow the Safety Guidelines.
Any graphic material provided in this documentation library is subject to variation and may not reflect the most recent updates or changes due to ongoing development and the implementation of new features.
Owing to periodic improvements of our products, the supplied products can differ in some details from the information stated in this documentation library. The information is subject to alteration without notice.
The English version of this documentation is the official and authoritative source of information. We make every effort to ensure that translations are accurate and clear; however, we do not accept responsibility for any errors, omissions, or misinterpretations in translated versions. In case of discrepancies, the English version will take precedence.